Project Specification
|
Name of project
|
Web Solutions Ltd.
|
|
Start date
|
13/11/12
|
|
Deadline
|
08/02/13
|
|
Stakeholders
|
Me, NHC
|
|
Business case requirements
|
·
To provide consultancy and web design services
to other businesses
·
To display my skills in creating a website
·
To display my knowledge of computer systems
|
|
Deliverables
|
Milestone 1
– 07/12/12
·
Articles on Wordpress
o Written
article “What’s Inside a Web Server? / Computer Hardware Explained”
o Written
recommendation for a Web Server
§ Explanation
of recommendation including low cost alternatives
o Animation/digital
poster/video “How the Internet Works”
§ Using
diagram of my website as an example
o Written
article “Website Performance Factors and the Benefits of Using Utility
Solutions”
§ Explanation
of Utility Solutions (maybe digital poster? If not, addition to written
article)
o Written
article “What is a Web Server? / Operating Systems Explained”
§ Include
reviews of available OSs
o Written
article “Internet Laws and Guidelines”
o Written
article “Security Measures for Web Servers”
o Digital
poster “Web 3.0 – Will It Work?”
·
Design work for Dreamweaver
o Site
Map
o Mood
board
o Storyboard
o Prototype
w/ asset list
Milestone 2
Milestone 3
|
|
Specific objectives
|
Create a
static Deamweaver site and a dynamic Wordpress site
|
|
Benefits and success factors
|
·
Cover all the topics listed
·
Having a professional looking website
·
Having good interview skills
·
Getting the job
|
|
Project boundaries
|
[enter scope]
|
|
Constraints
|
·
Cannot use Dreamweaver at home
·
Cannot use MS Office Project at home
·
Time in college is restricted
·
Trip planned on 30/11/12
|
|
Consideration of options
|
·
Create a blog to monitor progress
·
Table or blog for research log
·
I could use FRAPS to record examples of using
the internet
|
|
Consequences
|
Lowered final
grade for project, possible failure of units and possibly course.
|
|
Other
|
|
Good start but there is more than one stake holder. 4 objectives to be added to bis case req. confusing - is this for whole project or milestone 1? Getting the job might be a benefit?
ReplyDeletemake sure you plan around these constraints, don't forget about trips and the fact that a week equals 5 lessons. Options could discuss the format of the work that you are going to hand in.